1. TSO(s)*:
APG
2. Identification of affected Long Term Transmission Rights:
AT-IT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
01-11-2024 00:00 - 01:00 450 MW
01-11-2024 01:00 - 02:00 450 MW
01-11-2024 02:00 - 03:00 450 MW
01-11-2024 03:00 - 04:00 450 MW
01-11-2024 04:00 - 05:00 450 MW
01-11-2024 05:00 - 06:00 450 MW
01-11-2024 06:00 - 07:00 450 MW
01-11-2024 07:00 - 08:00 450 MW
01-11-2024 08:00 - 09:00 450 MW
01-11-2024 09:00 - 10:00 450 MW
01-11-2024 10:00 - 11:00 450 MW
01-11-2024 11:00 - 12:00 450 MW
01-11-2024 12:00 - 13:00 450 MW
01-11-2024 13:00 - 14:00 450 MW
01-11-2024 14:00 - 15:00 450 MW
01-11-2024 15:00 - 16:00 450 MW
01-11-2024 16:00 - 17:00 450 MW
01-11-2024 17:00 - 18:00 450 MW
01-11-2024 18:00 - 19:00 450 MW
01-11-2024 19:00 - 20:00 450 MW
01-11-2024 20:00 - 21:00 450 MW
01-11-2024 21:00 - 22:00 450 MW
01-11-2024 22:00 - 23:00 450 MW
01-11-2024 23:00 - 24:00 450 MW
5. Amount of LTTR remaining after curtailment:
01-11-2024 00:00 - 01:00 351 MW
01-11-2024 01:00 - 02:00 351 MW
01-11-2024 02:00 - 03:00 351 MW
01-11-2024 03:00 - 04:00 351 MW
01-11-2024 04:00 - 05:00 351 MW
01-11-2024 05:00 - 06:00 351 MW
01-11-2024 06:00 - 07:00 351 MW
01-11-2024 07:00 - 08:00 351 MW
01-11-2024 08:00 - 09:00 351 MW
01-11-2024 09:00 - 10:00 351 MW
01-11-2024 10:00 - 11:00 351 MW
01-11-2024 11:00 - 12:00 351 MW
01-11-2024 12:00 - 13:00 351 MW
01-11-2024 13:00 - 14:00 351 MW
01-11-2024 14:00 - 15:00 351 MW
01-11-2024 15:00 - 16:00 351 MW
01-11-2024 16:00 - 17:00 351 MW
01-11-2024 17:00 - 18:00 351 MW
01-11-2024 18:00 - 19:00 351 MW
01-11-2024 19:00 - 20:00 351 MW
01-11-2024 20:00 - 21:00 351 MW
01-11-2024 21:00 - 22:00 351 MW
01-11-2024 22:00 - 23:00 351 MW
01-11-2024 23:00 - 24:00 351 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected violation of operational security limits of physical transmission assets.
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.