Capacity Curtailment on the FR-IT border for delivery day 19/10/2021
1.TSO(s) *:
APG-ELES-RTE-SWG-TERNA
2. Identification of affected Long Term Transmission Rights
France to Italy
3. Triggering event:
☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
4. Affected volume in MW / hour for each concerned period:
France to Italy
19/10/2021
08:00 – 09:00 2415 MW
09:00 – 10:00 2415 MW
10:00 – 11:00 2415 MW
11:00 – 12:00 2415 MW
12:00 – 13:00 2415 MW
13:00 – 14:00 2415 MW
14:00 – 15:00 2415 MW
15:00 – 16:00 2415 MW
5. Amount of LTTR remaining after curtailment:
France to Italy
19/10/2021
08:00 – 09:00 1822 MW
09:00 – 10:00 1822 MW
10:00 – 11:00 1822 MW
11:00 – 12:00 1822 MW
12:00 – 13:00 1836 MW
13:00 – 14:00 1836 MW
14:00 – 15:00 1836 MW
15:00 – 16:00 1822 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
Violation on Lienz – Soverzene due to Critical outage DIVACA-REDIPUGLIA/DIVACA-PADRICIANO and Voltage stability issue on the Italian Electrical system
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.