Curtailment on the AT-IT border for delivery day 30/09/2022

Published: 29/09/2022 | 07:52

1. TSO(s)*: TERNA

2. Identification of affected Long Term Transmission Rights:

AT-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

30-09-2022 00:00 - 01:00 89 MW

30-09-2022 01:00 - 02:00 89 MW

30-09-2022 02:00 - 03:00 89 MW

30-09-2022 03:00 - 04:00 89 MW

30-09-2022 04:00 - 05:00 89 MW

30-09-2022 05:00 - 06:00 89 MW

30-09-2022 06:00 - 07:00 89 MW

30-09-2022 07:00 - 08:00 89 MW

30-09-2022 08:00 - 09:00 89 MW

30-09-2022 09:00 - 10:00 89 MW

30-09-2022 10:00 - 11:00 89 MW

30-09-2022 11:00 - 12:00 89 MW

30-09-2022 12:00 - 13:00 89 MW

30-09-2022 13:00 - 14:00 89 MW

30-09-2022 14:00 - 15:00 89 MW

30-09-2022 15:00 - 16:00 89 MW

30-09-2022 16:00 - 17:00 89 MW

30-09-2022 17:00 - 18:00 89 MW

30-09-2022 18:00 - 19:00 89 MW

30-09-2022 19:00 - 20:00 89 MW

30-09-2022 20:00 - 21:00 89 MW

30-09-2022 21:00 - 22:00 89 MW

30-09-2022 22:00 - 23:00 89 MW

30-09-2022 23:00 - 24:00 89 MW

5. Amount of LTTR remaining after curtailment:

30-09-2022 00:00 - 01:00 70 MW

30-09-2022 01:00 - 02:00 70 MW

30-09-2022 02:00 - 03:00 70 MW

30-09-2022 03:00 - 04:00 69 MW

30-09-2022 04:00 - 05:00 69 MW

30-09-2022 05:00 - 06:00 69 MW

30-09-2022 06:00 - 07:00 69 MW

30-09--2022 07:00 - 08:00 71 MW

30-09-2022 08:00 - 09:00 71 MW

30-09-2022 09:00 - 10:00 70 MW

30-09-2022 10:00 - 11:00 70 MW

30-09-2022 11:00 - 12:00 70 MW

30-09-2022 12:00 - 13:00 71 MW

30-09-2022 13:00 - 14:00 71 MW

30-09-2022 14:00 - 15:00 71 MW

30-09-2022 15:00 - 16:00 71 MW

30-09-2022 16:00 - 17:00 71 MW

30-09-2022 17:00 - 18:00 71 MW

30-09-2022 18:00 - 19:00 70 MW

30-09-2022 19:00 - 20:00 70 MW

30-09-2022 20:00 - 21:00 70 MW

30-09-2022 21:00 - 22:00 70 MW

30-09-2022 22:00 - 23:00 70 MW

30-09-2022 23:00 - 24:00 69 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Expected violation of operational security limits of physical transmission assets.

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.